New Premises – September Update

Building work continues a pace with both the electrical and mechanical teams now on site.

The stonework around the outside of the building is nearly complete and the external works to create the car park and paths have started.

The screed for the ground floor is complete and the lower ground floor screeding will be complete by the end of September, with plastering works due to start in October.

The roof tiling is complete and nearly all the external doors have been fitted.